2.
Implementation
|
i. |
The scheme is
implemented by the Directorate of Marketing and Inspection attached to Department of
Agriculture and Cooperation. Implementation of the scheme shall be continued up to
31.03.2007. |
ii. |
The construction
of godowns shall be as per specifications of Central /State/Public Works Deptt. Or any
other specifications laid down on this behalf. |
iii. |
The godown
complex shall have easy approach road, pucca internal roads, proper drainage, arrangements
for effective control against fire, theft and also have arrangements for easy loading and
unloading of stocks. |
iv. |
The entrepreneur
must have proper licence to operate such godowns under the State Warehousing Act or any
other relevant law. |
v. |
The project to
be prepared by the borrower acceptable to the bank and submitted along with approved plan
and estimated cost by an approved engineer. |
vi. |
Average DSCR
should not be below 1.5 and in any year it should not be less than 1.33. |
vii. |
As this is a
subsidy based scheme disbursement to be made only after receiving of 50% advance subsidy.
|